Our 14-Stage Pool Construction Process

Our 14-Stage Pool Construction Process

Professional Pool Company uses a documented, stage-by-stage build system so your project stays organized, compliant, and predictable — from engineering to final pool school.

Start a 3D Design Client Portal

Stage 1 — Engineering & Permitting

We confirm site constraints, finalize design details, and prepare engineered plans for permit submission.

  • Survey review + layout feasibility
  • Engineered plan set
  • Permit submission + tracking

Stage 2 — Layout

We mark your pool and deck footprint on-site to confirm placement before excavation.

  • Set elevations + reference points
  • Confirm access and setbacks
  • Homeowner confirmation

Stage 3 — Excavation

We excavate to engineered depths and prep the base for steel and plumbing.

  • Dig to profile (3’–6’ or as designed)
  • Haul-off / spoil management
  • Jobsite safety setup

Stage 4 — Steel & Main Drains

Steel is installed to spec and main drains are set for safe circulation.

  • Rebar cage installed + tied
  • Main drains set (VGB compliant)
  • Bonding prep as required

Stage 5 — Pre-Plumbing

We run plumbing lines and set suction/returns for performance and serviceability.

  • Skimmer + suction lines
  • Returns + features (if selected)
  • Pressure test prep

Stage 6 — Gunite

The structural shell is applied at high PSI to create the pool’s long-term foundation.

  • Shell shot + shaped
  • Benches / steps / sunshelf formed
  • Curing guidance provided

Stage 7 — Pre-Grade & Equipment Set

We prep grades and set equipment locations so everything fits and drains correctly.

  • Equipment pad location verified
  • Rough grades established
  • Utility coordination

Stage 8 — Tile & Coping / Cantilever

Waterline tile and coping/cantilever are installed for finish quality and clean lines.

  • Tile installed + leveled
  • Coping/cantilever formed + poured
  • Alignment checks

Stage 9 — Decking

Decking is installed per the approved selection (concrete acrylic, pavers, travertine, etc.).

  • Bond wire as required
  • Drainage + slope checks
  • Finish surface installed

Stage 10 — Electrical & Bonding

Electrical connections and bonding are completed to code so the system is safe and reliable.

  • Bonding verification
  • GFCI requirements met
  • Equipment power hookup

Stage 11 — Screen (If Applicable)

If your project includes a screen enclosure, it’s installed to engineered wind-load requirements.

  • Footers / tie-ins (if needed)
  • Structure install
  • Door hardware checks

Stage 12 — Safety Requirements

We confirm required Florida safety barriers (fence, alarms, etc.) are in place.

  • Barrier compliance check
  • Alarm / latch verification
  • Inspection readiness

Stage 13 — Interior Finish & Startup

Interior finish is applied, the pool is filled, equipment is started, and water is balanced.

  • Finish applied + fill coordination
  • Startup + chemical balance
  • Pool school + care guidance

Stage 14 — Final Inspection & Orientation

We coordinate final inspections and complete your final orientation walkthrough.

  • Final inspection scheduling
  • Punch list closeout
  • Owner manuals in Client Portal

Want a timeline and a real number?

Upload your property survey and backyard photos. We’ll build a 3D design and send an approximate proposal.

Request 3D Design

Updated on: 14/12/2025

Was this article helpful?

Share your feedback

Cancel

Thank you!