Construction timeline
Pool Construction Timeline
Professional Pool Company — What to Expect at Each Phase
Building a custom gunite pool involves several phases, each with specific inspections, engineering requirements, and quality control checks. While every property is unique, most projects follow a similar structure. This article explains the typical timeline from start to finish so homeowners know exactly what to expect.
⭐ 1. Design & Planning (1–2 Weeks)
Your project begins with:
- Custom 3D design
- Property layout planning
- Setback and zoning review
- Feature selection
- HOA preparation (if required)
Once the design is approved, we prepare your engineered plans for permitting.
⭐ 2. Engineering & Permitting (2–8 Weeks)
Duration depends on your county, HOA, and design complexity.
This phase includes:
- Structural engineering
- Screen enclosure engineering (if applicable)
- Equipment schematics
- Grading and drainage review
- County permit submission
- County or city review times
Some counties approve in as little as 2–3 weeks; others take longer depending on volume and review requirements.
⭐ 3. Pre-Construction Layout (1–3 Days)
Once the permit is issued, we:
- Mark out the pool location
- Confirm elevation
- Verify access path
- Review utilities and easements
A walkthrough may occur at this stage to confirm placement.
⭐ 4. Excavation (1–3 Days)
Your pool begins taking shape. This includes:
- Digging to engineered depths
- Shaping the pool outline
- Managing soil or groundwater conditions
- Preparing for steel installation
Tight access or special soil conditions may extend this phase slightly.
⭐ 5. Steel Reinforcement (1–3 Days)
Our team installs a complete structural steel grid based on engineering.
This includes:
- Bond beam structure
- Steel wall and floor grid
- Tie spacing
- Equipment bonding connections
A county inspection typically occurs once steel is in place.
⭐ 6. Plumbing, Electrical & Equipment Setup (2–4 Days)
This phase includes:
- Main drains
- Skimmer line installation
- Return lines
- Suction lines
- Spa plumbing (if applicable)
- Equipment pad setup
- Gas/electrical coordination
- Plumbing pressure test
Another inspection is required before gunite.
⭐ 7. Gunite / Shotcrete Shell (1 Day + Cure Time)
The structural shell is applied in one continuous session and shaped by hand.
After gunite, the shell must cure:
- Cure time: 21–28 days
- Light watering is performed regularly
- No construction on the shell during this period
This ensures long-term strength and durability.
⭐ 8. Tile, Coping & Decking (1–3 Weeks)
After curing, exterior finishes begin:
- Waterline tile
- Coping installation
- Deck preparation
- Decking material installation (pavers, concrete, travertine, etc.)
- Expansion joints and final grading
Larger or more complex decks may increase this phase.
⭐ 9. Screen Enclosure (If Included) (1–3 Days)
Screen enclosures require:
- Engineering approval
- Fabrication
- Installation
- Wind-load compliance
This step often occurs after decking is complete.
⭐ 10. Interior Finish & Pool Start-Up (2–4 Days)
Interior finish is applied (pebble, quartz, or aggregate).
This phase includes:
- Final interior finish application
- Filling the pool with water
- Equipment startup
- Initial water balance
- Lighting and automation checks
⭐ 11. Final Walkthrough & Handover (1 Day)
Your project concludes with a complete orientation:
- Equipment training
- Automation setup
- Safety review
- Maintenance guidance
- Warranty overview
You’re now ready to enjoy your new pool.
⭐ Typical Total Timeline
While each home is unique, a normal timeline looks like:
- Design & Engineering: 2–4 weeks
- Permitting: 2–8 weeks
- Construction: 8–12 weeks
- Total Average: 12–20 weeks (varies by county & design complexity)
Factors that may extend the timeline:
- Rain or weather delays
- HOA approval times
- County permit backlog
- Access challenges
- Custom features
- Larger decks
- Screen enclosures
- Complex engineering needs
⭐ We Focus on Accuracy, Not Rushed Timelines
At Professional Pool Company, our priority is:
✔ Quality workmanship
✔ Engineering accuracy
✔ Code-compliant installation
✔ Long-term durability
We do not cut corners or rush structural phases simply to shorten the calendar.
⭐ Ready to Begin Your Project?
We’ll create your custom 3D design, confirm your county requirements, and outline your exact timeline.
👉 Start your free 3D design and estimate today.
Need help right now?
Call us at 321-252-7371 or schedule a design consultation at this link.
© 2025 Professional Pool Company. All rights reserved.
Updated on: 28/11/2025
Thank you!