Construction timeline

Pool Construction Timeline

Professional Pool Company — What to Expect at Each Phase

Building a custom gunite pool involves several phases, each with specific inspections, engineering requirements, and quality control checks. While every property is unique, most projects follow a similar structure. This article explains the typical timeline from start to finish so homeowners know exactly what to expect.


1. Design & Planning (1–2 Weeks)

Your project begins with:

  • Custom 3D design
  • Property layout planning
  • Setback and zoning review
  • Feature selection
  • HOA preparation (if required)

Once the design is approved, we prepare your engineered plans for permitting.


2. Engineering & Permitting (2–8 Weeks)

Duration depends on your county, HOA, and design complexity.

This phase includes:

  • Structural engineering
  • Screen enclosure engineering (if applicable)
  • Equipment schematics
  • Grading and drainage review
  • County permit submission
  • County or city review times

Some counties approve in as little as 2–3 weeks; others take longer depending on volume and review requirements.


3. Pre-Construction Layout (1–3 Days)

Once the permit is issued, we:

  • Mark out the pool location
  • Confirm elevation
  • Verify access path
  • Review utilities and easements

A walkthrough may occur at this stage to confirm placement.


4. Excavation (1–3 Days)

Your pool begins taking shape. This includes:

  • Digging to engineered depths
  • Shaping the pool outline
  • Managing soil or groundwater conditions
  • Preparing for steel installation

Tight access or special soil conditions may extend this phase slightly.


5. Steel Reinforcement (1–3 Days)

Our team installs a complete structural steel grid based on engineering.

This includes:

  • Bond beam structure
  • Steel wall and floor grid
  • Tie spacing
  • Equipment bonding connections

A county inspection typically occurs once steel is in place.


6. Plumbing, Electrical & Equipment Setup (2–4 Days)

This phase includes:

  • Main drains
  • Skimmer line installation
  • Return lines
  • Suction lines
  • Spa plumbing (if applicable)
  • Equipment pad setup
  • Gas/electrical coordination
  • Plumbing pressure test

Another inspection is required before gunite.


7. Gunite / Shotcrete Shell (1 Day + Cure Time)

The structural shell is applied in one continuous session and shaped by hand.

After gunite, the shell must cure:

  • Cure time: 21–28 days
  • Light watering is performed regularly
  • No construction on the shell during this period

This ensures long-term strength and durability.


8. Tile, Coping & Decking (1–3 Weeks)

After curing, exterior finishes begin:

  • Waterline tile
  • Coping installation
  • Deck preparation
  • Decking material installation (pavers, concrete, travertine, etc.)
  • Expansion joints and final grading

Larger or more complex decks may increase this phase.


9. Screen Enclosure (If Included) (1–3 Days)

Screen enclosures require:

  • Engineering approval
  • Fabrication
  • Installation
  • Wind-load compliance

This step often occurs after decking is complete.


10. Interior Finish & Pool Start-Up (2–4 Days)

Interior finish is applied (pebble, quartz, or aggregate).

This phase includes:

  • Final interior finish application
  • Filling the pool with water
  • Equipment startup
  • Initial water balance
  • Lighting and automation checks


11. Final Walkthrough & Handover (1 Day)

Your project concludes with a complete orientation:

  • Equipment training
  • Automation setup
  • Safety review
  • Maintenance guidance
  • Warranty overview

You’re now ready to enjoy your new pool.


Typical Total Timeline

While each home is unique, a normal timeline looks like:

  • Design & Engineering: 2–4 weeks
  • Permitting: 2–8 weeks
  • Construction: 8–12 weeks
  • Total Average: 12–20 weeks (varies by county & design complexity)

Factors that may extend the timeline:

  • Rain or weather delays
  • HOA approval times
  • County permit backlog
  • Access challenges
  • Custom features
  • Larger decks
  • Screen enclosures
  • Complex engineering needs


We Focus on Accuracy, Not Rushed Timelines

At Professional Pool Company, our priority is:

✔ Quality workmanship

✔ Engineering accuracy

✔ Code-compliant installation

✔ Long-term durability

We do not cut corners or rush structural phases simply to shorten the calendar.


Ready to Begin Your Project?

We’ll create your custom 3D design, confirm your county requirements, and outline your exact timeline.

👉 Start your free 3D design and estimate today.


Need help right now?

Call us at 321-252-7371 or schedule a design consultation at this link.


© 2025 Professional Pool Company. All rights reserved.

Updated on: 28/11/2025