Articles on: COUNTY-SPECIFIC ARTICLES

Building a pool in Orange County

Building a Pool in Orange County

Professional Pool Company — What Homeowners Should Know Before Building a Pool in Orange County, FL

Building a pool in Orange County (unincorporated) follows a different process from the City of Orlando. Orange County focuses heavily on drainage, setbacks, and correct documentation. Understanding the county’s requirements helps your project move smoothly from design to permitting.


1. Orange County vs. City of Orlando — They Are NOT the Same

Orange County has its own:

✔ Zoning department

✔ Stormwater/Drainage review

✔ Building review

✔ Separate inspection team

If your address says Orlando, you may still live in unincorporated Orange County, not the city.

We determine this during your consultation.


2. What Orange County Requires Before a Pool Permit Can Be Submitted

We cannot submit a pool permit until the following items are complete:

1. Engineered Pool Plans

Signed and sealed plans including:

  • Shell design
  • Steel schedule
  • Beam heights
  • Steps/benches
  • Spa plans (if applicable)

2. Current Property Survey

Survey must show:

  • Setbacks
  • Easements
  • Drainage arrows
  • Home footprint
  • Utility lines
  • Elevations

Surveys missing elevation data commonly trigger corrections.

3. Site Plan (Plot Plan)

Orange County requires:

  • Exact pool location
  • Deck footprint
  • Equipment pad location
  • Setback measurements
  • Access path
  • Drainage flow direction

4. Drainage / Stormwater Notes

Orange County almost always requires:

  • Runoff direction arrows
  • Impervious area calculations
  • Confirmation that deck/pool won’t block drainage
  • Potential French drain placement (if needed)

5. HOA Approval (if applicable)

Required in many communities, including:

  • Horizon West
  • Waterford Trails
  • Avalon Park
  • Dr. Phillips
  • Hunters Creek
  • Lake Nona-area developments

Permitting cannot proceed without HOA approval where required.


3. Orange County Permitting Timeline

Typical Review Time:

3–6 weeks

County Review Departments:

  • Zoning
  • Stormwater / Engineering
  • Building / Structural
  • Environmental review (if applicable)
  • Corrections & resubmittals

Orange County is busier than Lake or Brevard, but faster than Seminole and Osceola in most cases.


4. Property Considerations Unique to Orange County

1. Drainage Enforcement

Orange County has strict stormwater requirements.

You may need:

  • Grading notes
  • Drainage corrections
  • Impervious area confirmation
  • Swale preservation

Drainage is the most common reason for permit delays.


2. Narrow Side Yard Access

Many homes in Orange County suburbs have:

  • AC units blocking access
  • Fence lines close to homes
  • Shared drainage easements

We inspect access before excavation.


3. High Water Table Pockets

Certain Orlando-area neighborhoods have shallow water tables, requiring:

  • Dewatering
  • Overflow drains
  • Special engineering notes


4. Septic System Setbacks

If your home uses septic (many older Orange County homes do):

We must document:

  • Tank location
  • Drainfield
  • Reserve area
  • Required setbacks

Septic conflicts may affect pool location.


5. Trees & Protected Shade Trees

Not as strict as the City of Orlando, but:

  • Some neighborhoods require tree replacement
  • Large oaks may restrict placement
  • Root zones must be avoided


5. Required Orange County Inspections

Orange County requires several inspections during construction:

1. Steel Inspection

Before gunite.

2. Electrical Bonding Inspection

Ensures pump, rebar, heater, and salt system are bonded correctly.

3. Plumbing Pressure Test

Verifies all lines hold pressure.

4. Deck/Footer Inspection

Needed for:

  • Pavers
  • Concrete deck
  • Screen enclosure footers

5. Final Inspection

Inspector checks:

  • Safety barrier compliance
  • Setbacks
  • Equipment operation
  • Drainage compliance
  • Interior finish
  • Gate/alarm systems

Final approval is required before completion.


6. Orange County Safety Requirements

Orange County follows Florida Building Code:

✔ 4’ barrier minimum

✔ Baby barrier

✔ Self-closing gates

✔ Door/window alarms

✔ Screen enclosure with latching doors

Barrier must be installed before the final inspection.


7. Construction Timeline After Permit Approval

After your permit is approved:

  1. Excavation – 1–2 days
  2. Plumbing & Steel – 2–4 days
  3. Inspections – 1–3 days
  4. Gunite – 1 day + curing
  5. Tile & Coping – 2–4 days
  6. Deck installation – 3–7 days
  7. Interior finish & startup – 2–3 days

Typical total timeline:

12–18 weeks, depending on weather, access, and material choices.


8. Tips for a Smooth Orange County Project

✔ HOA approval early

HOAs often meet monthly.

✔ Provide current survey

Old or incomplete surveys cause major delays.

✔ Expect drainage questions

Stormwater review is detailed.

✔ Clear equipment access

Tight side yards are common; access must be evaluated.

✔ Understand realistic timelines

Orange County is consistent but thorough.


9. Summary: Building a Pool in Orange County

Homeowners can expect:

✔ 3–6 week permitting timeline

✔ Detailed stormwater review

✔ HOA approvals when required

✔ Multiple county inspections

✔ 12–18 week construction duration

✔ Smooth build when documents are complete

Orange County is one of the most straightforward—but busiest—permitting offices in Central Florida.


Ready to Build Your Orange County Pool?

Professional Pool Company handles:

✔ 3D design

✔ Engineering

✔ HOA coordination

✔ All Orange County permitting

✔ Full construction

✔ Final inspection and startup

👉 Contact us anytime to begin your Orange County pool project.


Need help right now?

Call us at 321-252-7371 or schedule a design consultation at this link.


© 2025 Professional Pool Company. All rights reserved.

Updated on: 29/11/2025

Was this article helpful?

Share your feedback

Cancel

Thank you!