Building a pool in Orange County
Building a Pool in Orange County
Professional Pool Company — What Homeowners Should Know Before Building a Pool in Orange County, FL
Building a pool in Orange County (unincorporated) follows a different process from the City of Orlando. Orange County focuses heavily on drainage, setbacks, and correct documentation. Understanding the county’s requirements helps your project move smoothly from design to permitting.
⭐ 1. Orange County vs. City of Orlando — They Are NOT the Same
Orange County has its own:
✔ Zoning department
✔ Stormwater/Drainage review
✔ Building review
✔ Separate inspection team
If your address says Orlando, you may still live in unincorporated Orange County, not the city.
We determine this during your consultation.
⭐ 2. What Orange County Requires Before a Pool Permit Can Be Submitted
We cannot submit a pool permit until the following items are complete:
✔ 1. Engineered Pool Plans
Signed and sealed plans including:
- Shell design
- Steel schedule
- Beam heights
- Steps/benches
- Spa plans (if applicable)
✔ 2. Current Property Survey
Survey must show:
- Setbacks
- Easements
- Drainage arrows
- Home footprint
- Utility lines
- Elevations
Surveys missing elevation data commonly trigger corrections.
✔ 3. Site Plan (Plot Plan)
Orange County requires:
- Exact pool location
- Deck footprint
- Equipment pad location
- Setback measurements
- Access path
- Drainage flow direction
✔ 4. Drainage / Stormwater Notes
Orange County almost always requires:
- Runoff direction arrows
- Impervious area calculations
- Confirmation that deck/pool won’t block drainage
- Potential French drain placement (if needed)
✔ 5. HOA Approval (if applicable)
Required in many communities, including:
- Horizon West
- Waterford Trails
- Avalon Park
- Dr. Phillips
- Hunters Creek
- Lake Nona-area developments
Permitting cannot proceed without HOA approval where required.
⭐ 3. Orange County Permitting Timeline
Typical Review Time:
3–6 weeks
County Review Departments:
- Zoning
- Stormwater / Engineering
- Building / Structural
- Environmental review (if applicable)
- Corrections & resubmittals
Orange County is busier than Lake or Brevard, but faster than Seminole and Osceola in most cases.
⭐ 4. Property Considerations Unique to Orange County
✔ 1. Drainage Enforcement
Orange County has strict stormwater requirements.
You may need:
- Grading notes
- Drainage corrections
- Impervious area confirmation
- Swale preservation
Drainage is the most common reason for permit delays.
✔ 2. Narrow Side Yard Access
Many homes in Orange County suburbs have:
- AC units blocking access
- Fence lines close to homes
- Shared drainage easements
We inspect access before excavation.
✔ 3. High Water Table Pockets
Certain Orlando-area neighborhoods have shallow water tables, requiring:
- Dewatering
- Overflow drains
- Special engineering notes
✔ 4. Septic System Setbacks
If your home uses septic (many older Orange County homes do):
We must document:
- Tank location
- Drainfield
- Reserve area
- Required setbacks
Septic conflicts may affect pool location.
✔ 5. Trees & Protected Shade Trees
Not as strict as the City of Orlando, but:
- Some neighborhoods require tree replacement
- Large oaks may restrict placement
- Root zones must be avoided
⭐ 5. Required Orange County Inspections
Orange County requires several inspections during construction:
1. Steel Inspection
Before gunite.
2. Electrical Bonding Inspection
Ensures pump, rebar, heater, and salt system are bonded correctly.
3. Plumbing Pressure Test
Verifies all lines hold pressure.
4. Deck/Footer Inspection
Needed for:
- Pavers
- Concrete deck
- Screen enclosure footers
5. Final Inspection
Inspector checks:
- Safety barrier compliance
- Setbacks
- Equipment operation
- Drainage compliance
- Interior finish
- Gate/alarm systems
Final approval is required before completion.
⭐ 6. Orange County Safety Requirements
Orange County follows Florida Building Code:
✔ 4’ barrier minimum
✔ Baby barrier
✔ Self-closing gates
✔ Door/window alarms
✔ Screen enclosure with latching doors
Barrier must be installed before the final inspection.
⭐ 7. Construction Timeline After Permit Approval
After your permit is approved:
- Excavation – 1–2 days
- Plumbing & Steel – 2–4 days
- Inspections – 1–3 days
- Gunite – 1 day + curing
- Tile & Coping – 2–4 days
- Deck installation – 3–7 days
- Interior finish & startup – 2–3 days
Typical total timeline:
12–18 weeks, depending on weather, access, and material choices.
⭐ 8. Tips for a Smooth Orange County Project
✔ HOA approval early
HOAs often meet monthly.
✔ Provide current survey
Old or incomplete surveys cause major delays.
✔ Expect drainage questions
Stormwater review is detailed.
✔ Clear equipment access
Tight side yards are common; access must be evaluated.
✔ Understand realistic timelines
Orange County is consistent but thorough.
⭐ 9. Summary: Building a Pool in Orange County
Homeowners can expect:
✔ 3–6 week permitting timeline
✔ Detailed stormwater review
✔ HOA approvals when required
✔ Multiple county inspections
✔ 12–18 week construction duration
✔ Smooth build when documents are complete
Orange County is one of the most straightforward—but busiest—permitting offices in Central Florida.
⭐ Ready to Build Your Orange County Pool?
Professional Pool Company handles:
✔ 3D design
✔ Engineering
✔ HOA coordination
✔ All Orange County permitting
✔ Full construction
✔ Final inspection and startup
👉 Contact us anytime to begin your Orange County pool project.
Need help right now?
Call us at 321-252-7371 or schedule a design consultation at this link.
© 2025 Professional Pool Company. All rights reserved.
Updated on: 29/11/2025
Thank you!