Building a pool in Brevard County
Building a Pool in Brevard County
Professional Pool Company — What Homeowners Need to Know Before Building a Pool in Brevard County, FL
Brevard County has its own permit requirements, engineering standards, and inspection procedures that determine how long it takes to build a pool. This guide explains everything you need to know about building a pool in Brevard County, including county rules, required documents, timelines, inspections, and expectations.
⭐ 1. Overview of Pool Construction in Brevard County
Brevard County is known for:
✔ Quick permitting compared to other Central Florida counties
✔ Strict drainage and stormwater requirements
✔ Frequent elevation inspections
✔ Flood-zone evaluations in coastal areas
✔ HOA-heavy neighborhoods (Viera, Melbourne, Suntree)
Most pools take 3–5 weeks to receive a permit depending on workload and corrections.
⭐ 2. What Brevard County Requires Before a Pool Permit Is Submitted
To submit your pool permit, we must include:
✔ 1. Engineered Pool Plans
Stamped structural drawings showing steel, elevations, beam heights, and shell details.
✔ 2. Property Survey
Must show:
- Easements
- Buildable area
- Drainage patterns
- Utility lines
- Elevation (bench mark preferred)
✔ 3. Site Plan Drawing
Shows:
- Pool placement
- Setbacks
- Deck footprint
- Equipment location
- Access path
✔ 4. Drainage Plan (when required)
Some Brevard jurisdictions require:
- Swale maintenance
- Grade flow patterns
- Water runoff calculations
✔ 5. HOA Approval (if applicable)
HOA approval is typically needed in:
- Viera
- Suntree
- Merritt Island HOA communities
- Palm Bay subdivisions
Construction cannot begin until HOA and county approval are both complete.
⭐ 3. Typical Permitting Timeline in Brevard County
Average Review Time:
3–5 weeks
Includes:
- Intake review
- Building review
- Zoning review
- Environmental/erosion review (if needed)
- Floodplain review (in certain areas)
- Corrections (if required)
Faster Than:
Orange, Osceola, Volusia
Brevard is generally predictable and efficient with pool permits.
⭐ 4. Property Considerations Unique to Brevard County
✔ 1. Flood Zones Near the Coast
Pools in flood zones may require:
- Elevation certificates
- Special engineering notes
- Additional drainage planning
- Deck elevation adjustments
✔ 2. Utility Easements
Many Brevard lots have rear utility easements that limit how far back a pool can be placed.
✔ 3. Drainage Flow Requirements
Brevard often requires that pools and decks do not alter existing drainage flow to adjacent homes.
✔ 4. Space for Equipment
County rules require equipment to meet setbacks, usually:
- 5 ft from property lines
- Clear access for service
✔ 5. Sewer/Septic Considerations
If you have septic:
- Setbacks must be met
- Drainfields must be shown
- Additional engineering may be required
⭐ 5. Inspections Required by Brevard County
During pool construction, Brevard County requires:
1. Steel Inspection
Before gunite is applied.
2. Electrical Bonding Inspection
Ensures safety bonding is correct.
3. Plumbing Pressure Test Inspection
Confirms plumbing lines hold required pressure.
4. Deck or Footer Inspection
If installing pavers, concrete, or enclosure footers.
5. Final Inspection
Includes:
- Safety barrier compliance
- Pool equipment operation
- Alarms or fencing verification
- Deck drainage
- Access protection
No pool can be filled until the inspector approves all required phases.
⭐ 6. Brevard County Safety Requirements
Brevard follows Florida Building Code pool safety laws:
✔ Acceptable safety barriers:
- 4-foot perimeter fence
- Baby barrier around pool
- Door/window alarms leading to pool area
- Screen enclosure
- Self-latching gates
A safety solution must be installed before the final inspection.
⭐ 7. Expected Construction Timeline
After permitting, construction typically includes:
- Excavation – 1–2 days
- Plumbing & Steel – 2–4 days
- Inspection phase – 1–3 days
- Gunite – 1 day (+ curing time)
- Tile & Coping – 2–4 days
- Deck installation – 3–7 days
- Interior finish & startup – 2–3 days
Average total construction time:
10–16 weeks depending on weather and material choice.
⭐ 8. County-Specific Tips for a Smooth Build
✔ Submit HOA early
Some HOA boards meet only once per month.
✔ Have your survey ready
Missing surveys delay engineering.
✔ Understand drainage
Brevard takes stormwater seriously; backyard grading matters.
✔ Keep access clear
Equipment must pass through side yards carefully.
✔ Expect inspection scheduling gaps
Most inspections are next-day, but seasonal delays may occur.
⭐ 9. Summary: Building a Pool in Brevard County
Homeowners can expect:
✔ 3–5 week permitting timeline
✔ Clear county guidelines
✔ Important drainage and elevation considerations
✔ Multiple inspections throughout the build
✔ Strict safety barrier requirements
✔ Predictable construction flow after approvals
Brevard is one of the more straightforward counties for pool construction, but proper engineering and drainage planning are essential for fast approval.
⭐ Building in Brevard County? We Handle Every Step.
Professional Pool Company manages:
✔ Engineering
✔ Permitting
✔ HOA coordination
✔ County inspections
✔ Safety compliance
✔ Full construction process
👉 Contact us anytime to start your Brevard County pool build.
Need help right now?
Call us at 321-252-7371 or schedule a design consultation at this link.
© 2025 Professional Pool Company. All rights reserved.
Updated on: 29/11/2025
Thank you!